Thursday, 02 October 2014 00:00

Century Downs Construction Update (Oct.2) (video)

Written by Century Downs
Rate this item
(1 Vote)

As of October 2, 2014 Pre-cast walls are in place and steel stud wall is finishing up on the trackside façade. The floors inside the REC will be poured over the next week. The racetrack is awaiting fine grading and the underground utilities in the barn area are wrapping up. The next two weeks will be a flurry of activity inside and outside as the track material is laid and barn and maintenance building foundations are set.

(Video updated Oct. 8)

Read 1196 times Last modified on Wednesday, 08 October 2014 17:34

Media

Drone fly-over of Century Downs construction progress Century Downs